Question

17 - Use this information for Harry Company to answer the question that follow. The following...

17 - Use this information for Harry Company to answer the question that follow. The following data are given for Harry Company:

Budgeted production 1,069 units
Actual production   909 units
Materials:
    Standard price per ounce $1.85
    Standard ounces per completed unit 12
    Actual ounces purchased and used in production 11,235
    Actual price paid for materials $23,032
Labor:
    Standard hourly labor rate $14.44 per hour
    Standard hours allowed per completed unit 4.2
    Actual labor hours worked 4,681
    Actual total labor costs $76,066
Overhead:
    Actual and budgeted fixed overhead $1,032,000
    Standard variable overhead rate $27.00 per standard labor hour
    Actual variable overhead costs $131,068

Overhead is applied on standard labor hours. (Round interim calculations to the nearest cent.)

The direct labor rate variance is

a.$8,472.61 favorable

b.$20,936.97 unfavorable

c.$8,472.61 unfavorable

d.$20,936.97 favorable

Homework Answers

Answer #1

Option . C $ 8,472.61 unfavorable is correct answer

Direct labour rate variance

Actual labour hours worked( standard rate per hour - actual rate per hour)

Actual rate per hour = actual total labour ÷ Actual hours worked

So by putting value we can find actual rate per hour

$76066 ÷ 4681= 16.2499$ or rounded to nearest cent is $ $16.25

Actual hours worked= 4681

Standard labour rate per hour= $14.44

Actual labour rate per hour = $ 16.25

Labour rate variance

4681($14.44 -$16.25)= ($8472.61) or we can say

$8472.61 unfavorable

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Use this information for Stringer Company to answer the question that follow. The following data are...
Use this information for Stringer Company to answer the question that follow. The following data are given for Stringer Company: Budgeted production 959 units Actual production   1,063 units Materials:     Standard price per ounce $1.9     Standard ounces per completed unit 10     Actual ounces purchased and used in production 10,949     Actual price paid for materials $22,445 Labor:     Standard hourly labor rate $14.96 per hour     Standard hours allowed per completed unit 4.6     Actual labor hours worked 5,474.45     Actual total labor costs $83,485 Overhead:...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per...
20. Flapjack Corporation had 8,002 actual direct labor hours at an actual rate of $12.00 per hour. Original production had been budgeted for 1,100 units, but only 994 units were actually produced. Labor standards were 7.6 hours per completed unit at a standard rate of $12.86 per hour. The direct labor rate variance is a.$6,881.72 unfavorable b.$6,881.72 favorable c.$5,577.18 unfavorable d.$5,577.18 favorable 21. Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.08 per hour. Original...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual...
Q1: The standard costs and actual costs for direct materials for the manufacture of 2,600 actual units of product are Standard Costs Direct materials (per completed unit) 1,040 kilograms @$8.61 Actual Costs Direct materials 2,600 kilograms @ $8.20 Round your final answer to the nearest dollar. The amount of direct materials price variance is $426 favorable $426 unfavorable $1,066 favorable $1,066 unfavorable Q2: The standard costs and actual costs for direct materials for the manufacture of 2,650 actual units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of...
The standard costs and actual costs for factory overhead for the manufacture of 3,000 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit @ $0.72 per hour Variable overhead 3 hours per unit @ $2.06 per hour Actual Costs     Total variable cost, $18,000     Total fixed cost, $7,900 The fixed factory overhead volume variance is a.$720 unfavorable b.$0 c.$576 unfavorable d.$576 favorable The following data are given for Bahia Company: Budgeted...
Requirement: 1 Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours...
Requirement: 1 Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 6.4 ounces $ 3.00 per ounce $ 19.20 Direct labor 0.7 hours $ 19.00 per hour $ 13.30 Variable overhead 0.7 hours $ 3.00 per hour $ 2.10 The company reported the following results concerning this product in February. Originally budgeted output 4,700 units Actual output 5,200 units Raw materials used in production 30,400...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of...
The standard costs and actual costs for factory overhead for the manufacture of 2,800 units of actual production are as follows: Standard Costs Fixed overhead (based on 10,000 hours) 3 hours per unit at $0.71 per hour Variable overhead 3 hours per unit at $2.06 per hour Actual Costs Total variable cost, $18,000 Total fixed cost, $8,000 The fixed factory overhead volume variance is a.$0 b.$909 unfavorable c.$1,136 unfavorable d.$909 favorable
Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...
Majer Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 6.8 ounces $ 3.00 per ounce $ 20.40 Direct labor 0.4 hours $ 15.00 per hour $ 6.00 Variable overhead 0.4 hours $ 3.00 per hour $ 1.20 The company reported the following results concerning this product in February. Originally budgeted output 5,400 units Actual output 8,200 units Raw materials used in production 30,500 ounces Actual...
Budgeted production 26,000 units Actual production 27,500 units Labor:   Standard hourly labor rate $22 per hour...
Budgeted production 26,000 units Actual production 27,500 units Labor:   Standard hourly labor rate $22 per hour   Standard hours allowed per completed unit 6.6   Actual labor hours worked 183,000   Actual total labor costs $4,020,000 What is the labor price variance? 5,490 unfavorable 5,490 favorable 33,000 favorable 33,000 unfavorable
Tharaldson Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...
Tharaldson Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 7.2 ounces $ 2.00 per ounce $ 14.40 Direct labor 0.3 hours $ 16.00 per hour $ 4.80 Variable overhead 0.3 hours $ 4.00 per hour $ 1.20 The company reported the following results concerning this product in June. Originally budgeted output 2,600 units Actual output 2,200 units Raw materials used in production 18,000 ounces Purchases...
Tharaldson Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price...
Tharaldson Corporation makes a product with the following standard costs: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct materials 6.3 ounces $ 2.00 per ounce $ 12.60 Direct labor 0.4 hours $ 11.00 per hour $ 4.40 Variable overhead 0.4 hours $ 6.00 per hour $ 2.40 The company reported the following results concerning this product in June. Originally budgeted output 3,300 units Actual output 2,600 units Raw materials used in production 19,500 ounces Purchases...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT