Direct materials purchases budget
Tobin’s Frozen Pizza Inc. has determined from its production budget the following estimated production volumes for 12'' and 16'' frozen pizzas for November:
Units | ||||
12" Pizza | 16" Pizza | |||
Budgeted production volume | 74,000 | 54,000 |
There are three direct materials used in producing the two types of pizza. The quantities of direct materials expected to be used for each pizza are as follows:
12" Pizza | 16" Pizza | ||||
Direct materials: | |||||
Dough | 0.55 | lb. per unit | 0.80 | lbs. per unit | |
Tomato | 0.25 | 0.40 | |||
Cheese | 0.70 | 1.20 |
In addition, Tobin’s has determined the following information about each material:
Dough | Tomato | Cheese | ||||
Estimated inventory, November 1 | 2,400 | lbs. | 1,200 | lbs. | 2,800 | lbs. |
Desired inventory, November 30 | 2,200 | lbs. | 1,400 | lbs. | 2,500 | lbs. |
Price per pound | $0.30 | $0.40 | $0.65 |
Prepare November's direct materials purchases budget for Tobin’s Frozen Pizza Inc. For those boxes in which you must enter subtracted or negative numbers use a minus sign. Round your final answers to the nearest dollar.
Tobin’s Frozen Pizza Inc. | ||||||||
Direct Materials Purchases Budget | ||||||||
For the Month Ending November 30 | ||||||||
Dough | Tomato | Cheese | Total | |||||
Units required for production: | ||||||||
12" pizza | ||||||||
16" pizza | ||||||||
Desired inventory, November 30 | ||||||||
Total units available | ||||||||
Estimated inventory, November 1 | ||||||||
Total units to be purchased | ||||||||
Unit price | x | $ | x | $ | x | $ | ||
Total direct materials to be purchased | $ | $ | $ | $ |
Ans:
Tobin’s Frozen Pizza Inc. | ||||
Direct Materials Purchases Budget | ||||
For the Month Ending November 30 | ||||
Direct Materials | Direct Materials | Direct Materials | ||
Dough | Tomato | Cheese | Total | |
Units required for production: | ||||
12" pizza | 40700 | 18500 | 51800 | |
16" pizza | 43200 | 21600 | 64800 | |
Desired inventory, November 30 | 2200 | 1400 | 2500 | |
Total units available | 86100 | 41500 | 119100 | |
Estimated inventory, November 1 | -2400 | -1200 | -2800 | |
Total units to be purchased | 83700 | 40300 | 116300 | |
Unit Price | x $0.30 | x $0.40 | x $0.65 | |
Total direct materials to be purchased | $25,110 | $16,120 | $75,595 | $116,825 |