Question

Predetermined Factory Overhead Rate.This company uses a Job Order cost system   Estimated costs and expenses=Engine parts= $754,900;...

Predetermined Factory Overhead Rate.This company uses a Job Order cost system   Estimated costs and expenses=Engine parts= $754,900; Shop direct labor= 55,100; shopand repair equip. depreciaattion= 42,800; shop supervisor salaries= 119,100; shop property tax= 2,1600; shop supplies 16,600; advertising expense= 15,100; Administrative office salaries= 64,900 Administrative office depreciation ecp.= 8,300 TOTAL cost and expenses = 1,594,300The average shop direct labor rate is $19 per hour. determine the predetermined shop overhead rate per direct labor hour. round to the nearest whole cent. I got 25.9 and it was wrong please help

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Predetermined Factory Overhead Rate Exotic Engine Shop uses a job order cost system to determine the...
Predetermined Factory Overhead Rate Exotic Engine Shop uses a job order cost system to determine the cost of performing engine repair work. Estimated costs and expenses for the coming period are as follows: Engine parts $1,159,000 Shop direct labor 846,000 Shop and repair equipment depreciation 79,500 Shop supervisor salaries 220,900 Shop property taxes 40,100 Shop supplies 30,800 Advertising expense 23,200 Administrative office salaries 99,700 Administrative office depreciation expense 12,700    Total costs and expenses $2,511,900 The average shop direct labor rate...
Exotic Engine Shop uses a job order cost system to determine the cost of performing engine...
Exotic Engine Shop uses a job order cost system to determine the cost of performing engine repair work. Estimated costs and expenses for the coming period are as follows: Engine parts $715,100 Shop direct labor 522,000 Shop and repair equipment depreciation 36,000 Shop supervisor salaries 100,100 Shop property taxes 18,200 Shop supplies 13,900 Advertising expense 14,300 Administrative office salaries 61,500 Administrative office depreciation expense 7,900    Total costs and expenses $1,489,000 The average shop direct labor rate is $18.00 per hour....
Hi I have a question I don't understand this problem I know I'm doing the right...
Hi I have a question I don't understand this problem I know I'm doing the right work. This is for accounting Predetermined Factory Overhead Rate Spring Street Engine Shop uses a job order cost system to determine the cost of performing engine repair work. Estimated costs and expenses for the coming period are as follows: Engine parts $875,000 Shop direct labor 660,000 Shop and repair equipment depreciation 44,500 Shop supervisor salaries 138,000 Shop property taxes 27,500 Shop supplies 10,000 Advertising...
Wheeler’s Bike Company manufactures custom racing bicycles. The company uses a job order cost system to...
Wheeler’s Bike Company manufactures custom racing bicycles. The company uses a job order cost system to determine the cost of each bike. Estimated costs and expenses for the coming year follow: Bike parts $ 346,800 Factory machinery depreciation 58,000 Factory supervisor salaries 138,000 Factory direct labor 210,175 Factory supplies 37,400 Factory property tax 27,250 Advertising cost 20,500 Administrative salaries 54,500 Administrative-related depreciation 24,200 Total expected costs $ 916,825 Required: 1. Calculate the predetermined overhead rate per direct labor hour if...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct...
Beckner Inc. is a job-order manufacturer. The company uses a predetermined overhead rate based on direct labor hours to apply overhead to individual jobs. For the current year, estimated direct labor hours are 150,000 and estimated factory overhead is $1,140,000. The following information is for September. Job X was completed during September, while Job Y was started but not finished. September 1, inventories: Materials $ 25,700 Work-in-process (All Job X) 55,100 Finished goods 107,300 Materials purchases $ 174,000 Direct materials...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 40,000 Total fixed manufacturing overhead cost $ 96,000 Variable manufacturing overhead per direct labor-hour $ 3.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 20 Total direct labor-hours 100 Direct materials $ 755 Direct labor cost $...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $195,940. Estimated direct labor cost was $465,600 for 19,400 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,940 hours) $ 46,561 Indirect costs Indirect labor 2,530 Indirect materials 3,360 Factory rent 3,230 Factory supervision 4,820 Factory...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on...
Verizox Company uses a job order cost system with manufacturing overhead applied to products based on direct labor hours. At the beginning of the most recent year, the company estimated its manufacturing overhead cost at $179,540. Estimated direct labor cost was $456,490 for 19,100 hours. Actual costs for the most recent month are summarized here: Item Description Total Cost Direct labor (1,910 hours) $ 45,650 Indirect costs Indirect labor 2,420 Indirect materials 3,430 Factory rent 3,370 Factory supervision 4,860 Factory...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Dehner Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on the following data: Total direct labor-hours 64,000 Total fixed manufacturing overhead cost $678,400 Variable manufacturing overhead per direct labor-hour $ 5.00 Recently, Job P951 was completed with the following characteristics: Number of units in the job 30 Total direct labor-hours 300 Direct materials $ 1,350 Direct labor cost $ 11,400...
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on...
Meenach Corporation uses a job-order costing system with a single plantwide predetermined overhead rate based on direct labor-hours. The company based its predetermined overhead rate for the current year on 58,000 direct labor-hours, total fixed manufacturing overhead cost of $58,000, and a variable manufacturing overhead rate of $2.90 per direct labor-hour. Recently Job X387 was completed and required 220 direct labor-hours. Required: Calculate the amount of overhead applied to Job X387