Job 412 was one of the many jobs started and completed during the year. The job required $9,400 in direct materials and 30 hours of direct labor time at a total direct labor cost of $10,300. If the job contained five units and the company billed at 75% above the unit product cost on the job cost sheet, what price per unit would have been charged to the customer?
Total cost of JOb 412:
Direct material: $9400
Direct labour: $10300
Overheads: $ 0
Total cost: $ 19,700
Add: mark-up (75% of cost: $ 14,775
Total Sales price of Job 412: $ 34,475
Number of units: 5 units
Selling price per unit: $ 6,895