Mouret Corporation uses the following activity rates from its activity-based costing to assign overhead costs to products.
Activity Cost Pools | Activity Rate | |||
Setting up batches | $ | 82.26 | per batch | |
Processing customer orders | $ | 62.90 | per customer order | |
Assembling products | $ | 1.78 | per assembly hour | |
Last year, Product N79A required 32 batches, 1 customer orders, and 367 assembly hours.
Required:
How much overhead cost would be assigned to Product N79A using the company's activity-based costing system? (Do not round your intermediate calculations. Round your final answer to two decimal places.)