Waterway's Bakery makes a variety of home-style cookies for
upscale restaurants in the Atlanta metropolitan area. The company's
best-selling cookie is the double chocolate almond supreme.
Waterway's recipe requires 80 ounces of a commercial cookie mix, 7
ounces of milk chocolate, and 2 ounces of almonds per batch of
cookies. The standard direct materials costs are $1.20 per pound of
cookie mix, $12.00 per pound of milk chocolate, and $10.00 per
pound of almonds. Each pound of cookies requires 1 minutes of
direct labor in the mixing department and 3 minutes of direct labor
in the baking department. The standard labor rates in those
departments are $12.00 per direct labor hour (DLH) and $22.00 per
DLH, respectively. Variable overhead is applied at a rate of $48.00
per DLH; fixed overhead is applied at a rate of $78.00 per
DLH.
Calculate the standard cost for a pound of Waterway's double
chocolate almond supreme cookies. (Round answer to 2
decimal places, e.g. 3.51.)
Standard cost per pound | $enter the standard cost per pound in dollars rounded to 2 decimal places |
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Waterway's Bakery | |||||
1 pound =16 ounces | |||||
Direct material cost per pound | Commercial cookie | Milk chocolate | Almonds | Total | Note |
Quantity required per pound (Ounces) | 80.00 | 7.00 | 2.00 | A | |
Quantity required per pound (Pound) | 5.00 | 0.44 | 0.13 | B=A/16 | |
Cost per pound | 1.20 | 12.00 | 10.00 | C | |
Direct material cost per pound | 6.00 | 5.25 | 1.25 | 12.50 | D=B*C |
Direct labor cost per pound | Mixing | Baking | Total | ||
Time required per pound (minutes) | 1.00 | 3.00 | E | ||
Time required per pound (Hours) | 0.02 | 0.05 | 0.07 | F=E/60 | |
Cost per hour | 12.00 | 22.00 | G | ||
Direct labor cost per pound | 0.20 | 1.10 | 1.30 | H=F*G | |
Overhead cost per pound | Amount $ | ||||
Variable overhead per hour | 48.00 | I | |||
Fixed overhead per hour | 78.00 | J | |||
Total overhead per hour | 126.00 | K=I+J | |||
Time required per pound (Hours) | 0.07 | See F | |||
Overhead cost per pound | 8.40 | L=K*F | |||
Standard cost for a pound | Amount $ | ||||
Direct material cost per pound | 12.50 | See D | |||
Direct labor cost per pound | 1.30 | See H | |||
Overhead cost per pound | 8.40 | See L | |||
Standard cost for a pound | 22.20 |