Question

Two types of materials are used as follows: Minimum usage 20 units per week each Maximum...

Two types of materials are used as follows:

Minimum usage 20 units per week each

Maximum usage 60 units per week each

Normal usage 40 units per week each

Re-order period or Lead time

Material A: 3 to 5 weeks

Material B: 2 to 4 weeks

Calculate reorder point for two types of materials?

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Question 4: The following information pertains to raw material ‘A’ used in production process of Part...
Question 4: The following information pertains to raw material ‘A’ used in production process of Part Pearl Inc., Normal usage 50 tons per week Maximum usage 75 tons per week Minimum usage 25 tons per week Re-ordering Quantity30 unit Re-order period (Lead Time) 4 to 6 weeks You are required to calculate for Raw material A: (a) Re-order Stock Level (b) Minimum Stock Level (c) Average stock level; and (d) Maximum stock level
Following information is available in respect of a particular material used by CTLS Limited. • Minimum...
Following information is available in respect of a particular material used by CTLS Limited. • Minimum materials consumption - 80 units per day • Maximum materials consumption - 120 units per day • Re-order quantity - 4 800 units • Re-order period - Minimum 20 days Maximum 30 days Using the above information, calculate; i. Re-order level ii. Maximum stock level iii. Minimum stock level iv. Average stock level
Sharon Ltd has in the past ordered raw material T in quantities of 3,000 units which...
Sharon Ltd has in the past ordered raw material T in quantities of 3,000 units which is half a year’s supply. Management has instructed you, an inventory cost consultant, to advise them as to the most desired order quantities. The factory closes for 4 weeks annual leave per annum. You are given the following data: Inventory usage rate: 125 per week, Lead time: 3 weeks Unit price: $1.50, Annual requirement: 6,000 units Order cost: $9.00 per order, Carrying cost: $0.30...
The Cheap Store starts with 700 units stocks every week. The stock is used up each...
The Cheap Store starts with 700 units stocks every week. The stock is used up each week and a reorder is made to replace the used up items. If the yearly carrying cost per unit is RM20 and the fixed order cost is RM80. (Note: there are 52 weeks in a year). Calculate the i. Carrying cost ii. Restocking Costs iii. The economic order quantity iv. Number of orders per year v. DO you think that the company's inventory policy...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in...
Cress Electronic Products manufactures components used in the automotive industry. Cress purchases parts for use in its manufacturing operation from a variety of different suppliers. One particular supplier provides a part where the assumptions of the EOQ model are realistic. The annual demand is 2,500 units, the ordering cost is $40 per order, and the annual holding cost rate is 25%. (a) If the cost of the part is $20 per unit, what is the economic order quantity? (b) Assume...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2...
The demand for subassembly S is 120 units in week 7. Each unit of S requires2 units of T and 1 unit of U. Each unit of T requires 1 unit of​ V,1unit of​ W, and1 unit of X.​ Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make​ S,1week to make​ T, 2 weeks to make​ U, 2 weeks to make​ V, 3...
An audit senior at your place has requested you to undertake a review of the client’s...
An audit senior at your place has requested you to undertake a review of the client’s inventory system by determining the critical inventory levels, economic order quantity, cost of issues and valuation of closing inventory. The client file contains the following schedules in relation to inventory: Minimum Usage - 500 units per working week Maximum Usage - 3000 units per working week Average usage - 2500 units per week Lead time - 10 – 20 days Ordering costs - K260...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from...
Jill's Job Shop buys two parts (Tegdiws and Widgets) for use in its production system from two different suppliers. The parts are needed throughout the entire 52-week year. Tegdiws are used at a relatively constant rate and are ordered whenever the remaining quantity drops to the reorder level. Widgets are ordered from a supplier who stops by every five weeks. Data for both products are as follows:   ITEM TEGDIW WIDGET   Annual demand 13,000 6,000   Holding cost (% of item cost)...
Staples sells 500 HP printers every week (assume 52 weeks per year). Each printer costs $100...
Staples sells 500 HP printers every week (assume 52 weeks per year). Each printer costs $100 and Staples has a holding cost of 20 percent. The fixed cost for each order Staples places with HP is $800. Find the EOQ, total annual cost, reorder point, number of orders per year, and the time between orders.
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day...
Choose the right answer: A product’s usage is normally distributed with average demand of 400 units/day and a weekly standard deviation of 125. The product’s lead time is 20 days. Currently, the reorder point for this product is 8,200. The company work 5 days per week. If the company would like to have a service level of 95% for this product then A. it must decrease its safety stock by approximately 412 units. B. it must decrease its safety stock...