Question

LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length...

LaCrosse, Inc., sales manager Josh Brown has been receiving calls from customers complaining about the length of time it takes to receive an order. To help him understand the issue, he gathered the following information from DanGold Enterprises’ most recent order.

Days Required
Process customer order 0.1
Wait for direct materials to arrive 4.0
Fabrication of parts 4.0
Move order to assembly department 0.5
Wait for machine time 6.0
Assembly of parts 4.0
Move order to finishing department 0.3
Wait for machine time 3.0
Finishing of units 6.0
Move to packing department 0.9
Packing 1.7
Move to shipping department 0.2
Load delivery truck 0.5
Drive to customer 0.5
Unload delivery truck 0.7
Return to plant 2.0
Enter the delivery cycle time in days rounded to 1 decimal place.
enter the manufacturing cycle time in days rounded to 1 decimal place.
Enter the value-added time in days rounded to 1 decimal place.

Homework Answers

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time...
Management of Mittel Rhein AG of Köln, Germany, would like to reduce the amount of time between when a customer places an order and when the order is shipped. For the first quarter of operations during the current year the following data were reported: Inspection time 0.5 days Wait time (from order to start of production) 16.2 days Process time 3.2 days Move time 1.5 days Queue time 4.0 days Required: 1. Compute the throughput time. (Round your answer to...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible...
DataSpan, Inc., automated its plant at the start of the current year and installed a flexible manufacturing system. The company is also evaluating its suppliers and moving toward Lean Production. Many adjustment problems have been encountered, including problems relating to performance measurement. After much study, the company has decided to use the performance measures below, and it has gathered data relating to these measures for the first four months of operations. Month 1 2 3 4 Throughput time (days) ?...
In an effort to evaluate performance and determine where improvements can be made, management has gathered...
In an effort to evaluate performance and determine where improvements can be made, management has gathered the following data relating to activities over the last four months: Month 1 2 3 4 Quality control measures: Number of defects 201 179 140 98 Number of warranty claims 62 55 46 43 Number of customer complaints 118 112 95 74 Material control measures: Purchase order lead time 10 days 9 days 7 days 5 days Scrap as a percent of total cost...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft...
The Boeing Company, headquartered in Chicago, Illinois, is one of the two major producers of aircraft in the global market. The other major producer is European Airbus. Boeing produces three models in Everett, Washington: 747s, 767s, and 777s. The planes are all produced in the same building. At any one time, there may be as many as six planes in various stages of production. Obviously the building has to be fairly large to accommodate such a huge undertaking. In fact,...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From...
Sign In INNOVATION Deep Change: How Operational Innovation Can Transform Your Company by Michael Hammer From the April 2004 Issue Save Share 8.95 In 1991, Progressive Insurance, an automobile insurer based in Mayfield Village, Ohio, had approximately $1.3 billion in sales. By 2002, that figure had grown to $9.5 billion. What fashionable strategies did Progressive employ to achieve sevenfold growth in just over a decade? Was it positioned in a high-growth industry? Hardly. Auto insurance is a mature, 100-year-old industry...