Assume Drake Consulting has created a standard cost card for
each job. Standard direct materials per job include14 software
packages at a cost of $900 per package. Standard direct labor costs
per job include 120 hours at $ 100 per hour. Drake plans on
completing 10 jobs during March 2018.
Actual direct materials costs for March included 90 software
packages at a total cost of $81,450. Actual direct labor costs
included 145 hours per job at an average rate of $105 per hour.
Drake completed all 10 jobs in March.
1.Calculate direct materials cost and efficiency
variances.
2.Calculate direct labor cost and efficiency variances.
3. Prepare journal entries to record the use of both materials and
labor for March for the company.