Fellar Corp. has identified the following
information:
Activity cost pools | |
Materials handling | $48,720 |
Machine maintenance | 16,500 |
Cost drivers | |
Number of material moves | 870 |
Number of machine hours | 66,000 |
Required:
1. Calculate the activity rate for each cost pool.
(Round your answers to 2 decimal places.)
2. Determine the amount of overhead assigned to
Fellar’s products if they have the following activity demands:
(Round your intermediate calculations to 2 decimal places
and final answers to the nearest whole dollar
amount.)
Product A | Product B | ||
Number of material moves | 520 | 350 | |
Number of machine hours | 41,900 | 24,100 | |
1. Calculate the activity rate for each cost pool.
Activity cost pool | activity rate |
material handling (48720/870) | 56 per moves |
Machine maintenance (16500/66000) | 0.25 per machine hour |
2. Determine the amount of overhead assigned to Fellar’s products if they have the following activity demands
Product A | Product B | |
Material handling | 56*520 = 29120 | 56*350=19600 |
Machine maintenance | 41900*.25=10475 | 24100*.25=6025 |
Total overhead | 39595 | 25625 |