Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs were incurred as follows: $18000.....Utilities (a variable cost) $35300.....Maintenance (a mixed cost) $21000......Supervisor salaries (a fixed cost) $74300....Total overhead in March Total overhead in April was $87050 and machine-hours in April was 4500. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have been for Maintenance?
Answer 1
Computation of cost for Utilities in April
Particular | Amount ($) | |
---|---|---|
Total Utilities in March | 18,000 | |
Machine Hours used in March | 3000 machine-hours. | |
Cost Per Machine Hrs : ($18,000 / 3,000 hrs) | 6 | |
Machine Hrs used in April | 4,500 machine-hours | |
Total Utilities cost in April : 4,500 machine-hours * $6 | $27,000 |
Answer 2
Note : Supervisor salaries is a fixed cost , thus will remain same fot March & april ie $21000 per month
Computation of Maintenance cost for April.
Particular | Amount ($) |
---|---|
Total overhead cost in April | 87,050 |
Less : Total Utilities cost in April (refer Answer 1 ) | (27,000) |
Less : Supervisor salaries for April | (21,000) |
Maintenance cost in April. | 39,050 |