Question

Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs...

Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 3000 machine-hours. Manufacturing overhead costs were incurred as follows: $18000.....Utilities (a variable cost) $35300.....Maintenance (a mixed cost) $21000......Supervisor salaries (a fixed cost) $74300....Total overhead in March Total overhead in April was $87050 and machine-hours in April was 4500. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have been for Maintenance?

Homework Answers

Answer #1

Answer 1

Computation of cost for Utilities in April

Particular Amount ($)
Total Utilities in March 18,000
Machine Hours used in March 3000 machine-hours.
Cost Per Machine Hrs : ($18,000 / 3,000 hrs) 6
Machine Hrs used in April 4,500 machine-hours
Total Utilities cost in April : 4,500 machine-hours * $6 $27,000

Answer 2

Note : Supervisor salaries is a fixed cost , thus will remain same fot March & april ie $21000 per month

Computation of Maintenance cost for April.

Particular Amount ($)
Total overhead cost in April 87,050
Less : Total Utilities cost in April (refer Answer 1 ) (27,000)
Less : Supervisor salaries for April (21,000)
Maintenance cost in April. 39,050
Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs...
Neevey Inc. tracks activity based on machine-hours. In March, Neevy used 2900 machine-hours. Manufacturing overhead costs were incurred as follows: $14500.....Utilities (a variable cost) $35050..... Maintenance (a mixed cost) $18000...... Supervisor salaries (a fixed cost) $67550.... Total overhead in March Total overhead in April was $89400 and machine-hours in April was 5200. Do not enter expenses as negative numbers. 1. How much of the April overhead must have been for Utilities? 2. How much of the April overhead must have...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total...
Crosshill Company’s total overhead costs at various levels of activity are presented below: Month Machine-Hours Total Overhead Cost      April 49,000    $173,870        May 39,000    $151,570        June 59,000    $196,170        July 69,000    $218,470   Assume that the overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 39,000-machine-hour level of activity in May is as follows:   Utilities (variable) $ 42,900     Supervisory salaries (fixed) 46,000   Maintenance (mixed) 62,670   Total overhead cost $ 151,570 The...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 52,000 $ 198,260 May 42,000 $ 172,460 June 62,000 $ 224,060 July 72,000 $ 249,860 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 42,000 machine-hour level of activity is: Utilities (variable) $ 58,800 Supervisory salaries (fixed) 49,000 Maintenance (mixed) 64,660 Total overhead cost $ 172,460 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 217,820 May 38,000 $ 190,420 June 58,000 $ 245,220 July 68,000 $ 272,620 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 70,000 Maintenance (mixed) 63,420 Total overhead cost $ 190,420 Nova Company’s...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours...
Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 48,000 $ 199,940 May 38,000 $ 172,640 June 58,000 $ 227,240 July 68,000 $ 254,540 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 38,000 machine-hour level of activity is: Utilities (variable) $ 57,000 Supervisory salaries (fixed) 54,000 Maintenance (mixed) 61,640 Total overhead cost $ 172,640 Nova Company’s...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours...
Prince Company’s total overhead costs at various levels of activity are presented below:   Month Machine Hours Total Overhead Cost   September 112,800 $ 781,512   October 89,200 $ 662,568   November 157,200 $ 1,005,288   December 165,000 $ 1,044,600 Assume that the overhead cost above consists of utilities, supervisory salaries, depreciation, and maintenance. The breakdown of these costs at the 89,200-machine-hour level of activity in October is as follows:   Utilities (variable) $ 233,704   Supervisory salaries       and depreciation (fixed) 172,000   Maintenance (mixed)      256,864   Total overhead...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of...
Problem 5A-8 High-Low Method; Predicting Cost [LO5-10] Nova Company’s total overhead cost at various levels of activity are presented below: Month Machine- Hours Total Overhead Cost April 51,000 $ 181,360 May 41,000 $ 157,760 June 61,000 $ 204,960 July 71,000 $ 228,560 Assume that the total overhead cost above consists of utilities, supervisory salaries, and maintenance. The breakdown of these costs at the 41,000 machine-hour level of activity is: Utilities (variable) $ 53,300 Supervisory salaries (fixed) 48,000 Maintenance (mixed) 56,460...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 2,600 machine-hours Variable overhead costs: Supplies $ 11,960 Indirect labor 22,100 Fixed overhead costs: Supervision 15,600 Utilities 6,000 Depreciation 7,000 Total overhead cost $ 62,660 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 2,500 machine-hours rather than 2,600 machine-hours? Multiple Choice $60,750 $60,250 $61,350 $62,660 . Petrus Framing's cost...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours...
Kerekes Manufacturing Corporation has prepared the following overhead budget for next month. Activity level 3,800 machine-hours Variable overhead costs: Supplies $ 22,040 Indirect labor 36,860 Fixed overhead costs: Supervision 16,900 Utilities 7,200 Depreciation 8,200 Total overhead cost $ 91,200 The company's variable overhead costs are driven by machine-hours. What would be the total budgeted overhead cost for next month if the activity level is 3,700 machine-hours rather than 3,800 machine-hours?
Question # 7 Dubai Heavy Industries (DHI) is manufacturing company whose total manufacturing overhead costs fluctuate...
Question # 7 Dubai Heavy Industries (DHI) is manufacturing company whose total manufacturing overhead costs fluctuate somewhat from year to year according to the number of machine-hours worked in its production facility. These costs at high and low levels of activity over recent years are given below: Level of Activity Low High Machine-hours 60,000 80,000 Total Manufacturing Overhead Costs $274,000 $312,000 The manufacturing overhead costs above consist of Indirect Materials, Rent, and Maintenance. The company has analyzed these costs at...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT