Mordica Company’s standard labor cost per unit of output is
$32.40 (2.70 hours x $12.00 per hour). During August, the company
incurs 2,970 hours of direct labor at an hourly cost of $10.80 per
hour in making 1,000 units of finished product.
Compute the total, price, and quantity labor variances.
(Round answers to 2 decimal places, e.g.
52.75.)
enter a dollar amount rounded to 2 decimal places |
select an option UnfavorableNeither favorable nor unfavorableFavorable | |||
enter a dollar amount rounded to 2 decimal places |
select an option Neither favorable nor unfavorableUnfavorableFavorable | |||
enter a dollar amount rounded to 2 decimal places |
select an option UnfavorableNeither favorable nor unfavorableFavorable |
Total - $324 Favourable.
Labor Price Variance = $3,564 Favourable.
Labor Quantity Variance = $3,240 Unfavourable.