Question

Delmonte Builders is currently working on a three-year building project for a client. Delmonte recognizes revenues...

Delmonte Builders is currently working on a three-year building project for a client. Delmonte recognizes revenues based on the percentage of the work completed by the end of each year. The following table shows the project progress over the three-year period.

Year 1 2 3
Total price of the three-year project $10,000,000 $10,000,000 $10,000,000
Percentage of the work completed 18% 75% 100%
Cash received from the client $3,500,000 $3,500,000 $3,000,000

REQUIRED: How much revenue should Delmonte recognize in Years 2 and 3? Explain.

Homework Answers

Answer #1

Revenue to be recognised in percentage completion method is based on the percentage of work completed. Revenue to be recognised in the subsequent year will be reduced from the Previously recognised revenue as the percentage of completion is on cumulative basis.

Revenue to be recognised = Total price*percentage of completion

Year 1 = 10,000,000*18% = 1,800,000

Year 2 = Total price*percentage of completion - Previously recognised

= 10,000,000*75% - 1,800,000

= $5,700,000

Year 3 = 10,000,000 - 1,800,000 - 5,700,000

= $2,500,000

If you find the answer helpful please upvote.

Know the answer?
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for?
Ask your own homework help question
Similar Questions
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a...
Revenue Recognition In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017     $35 million Construction in progress (as of 12/31/2017)                                                                                                    $50 million Accounts Receivable from construction billings (as...
On January 1, Year 1, Cumulus Contracting, Inc., entered into an agreement to construct a building...
On January 1, Year 1, Cumulus Contracting, Inc., entered into an agreement to construct a building on the customer's land. The project was expected to take 3 years and involve a total cost of $6,000,000. The client has agreed to pay Cumulus $9,000,000 upon completion of the building. Cumulus determined that revenue from this contract is recognized over time. Cumulus uses the input method based on costs incurred to measure progress toward completion of the contract. The following information about...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing...
In 2017, Chicago Construction began work on a three-year construction project to build a new performing arts complex (the "PAC"). Chicago uses the percentage-of-completion method of accounting. At the end of 2017, the company completed 25% of the project. The following financial statement information indicates the results to date for the PAC at the end of 2017: Actual Cost incurred in 2017                                                                                                                                                              $35 million Construction in progress (as of 12/31/2017)                                                                                                   $50 million Accounts Receivable from construction billings (as of...
A project requires an initial capex of $200,000 (at t=0) and is expected to produce revenues...
A project requires an initial capex of $200,000 (at t=0) and is expected to produce revenues of $300,000 per year and costs of $180,000 per year for two years (that is, at t = 1 and t = 2). The corporate tax rate is 30%. The assets will be depreciated using the MACRS 3-year schedule: Year Depreciation Percentage 1 33% 2 45% 3 15% 4 7% WACC is 12%. Assume that the capital asset will sell for book value at...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an...
1. On November 1, 2018, Taylor signed a one-year contract to provide handyman services on an as-needed basis to King Associates, with the contract to start immediately. King agreed to pay Taylor $5,400 for the one-year period. Taylor is confident that King will pay that amount, but payment is not scheduled to occur until 2019. Taylor should recognize revenue in 2018 in the amount of Multiple Choice a. $900 b. $2,700 c. $0 d. $5,400 2. Mary signed up and...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company...
Multiple Choice Question 103 Oriole Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1100000 each quarter. The total contract price is $13200000 and Oriole estimates total costs of $17300000. Oriole estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2019, Oriole Construction estimates that it is 75% complete with the building; however,...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract...
Citation Builders, Inc., builds office buildings and single-family homes. The office buildings are constructed under contract with reputable buyers. The homes are constructed in developments ranging from 10–20 homes and are typically sold during construction or soon after. To secure the home upon completion, buyers must pay a deposit of 10% of the price of the home with the remaining balance due upon completion of the house and transfer of title. Failure to pay the full amount results in forfeiture...
ADVERTISEMENT
Need Online Homework Help?

Get Answers For Free
Most questions answered within 1 hours.

Ask a Question
ADVERTISEMENT