Given below is an excerpt from a management performance report:
Budget | Actual | Difference | |
Contribution margin | $1,000,000 | $1,025,000 | $25,000 |
Controllable fixed costs | $ 500,000 | $ 475,000 | $25,000 |
The manager’s overall performance
The manager’s overall performance –
Is 10% above expectations, as shown below
Performance measurement –
Actual net income = actual contribution – actual fixed overhead = $1,025,000 - $475,000 = $550,000
Budgeted net income = budgeted contribution – budgeted fixed overhead
= $1,000,000 - $500,000 = $500,000
Performance measurement = increase in net income/budgeted net income
= (550,000 – 500,000)/500,000 = 10%
Hence, the manager’s overall performance is 10% above expectations.